PBC approves $4.1M in solar change orders

The Permanent Building Committee approved two solar change orders and found an accelerated AC schedule for two schools feasible. Members voted unanimously to approve a $1,950,441 change order for Honeywell and a $2,125,615 change order for Hardy Solar, both authorizing Steve Gagosian to sign.

Email Text Facebook X

Permanent Building Committee · Meeting of September 10, 2026

WELLESLEY — The Permanent Building Committee approved two solar change orders and found an accelerated AC schedule for two schools feasible. Members voted unanimously to approve a $1,950,441 change order for Honeywell and a $2,125,615 change order for Hardy Solar, both authorizing Steve Gagosian to sign. The committee also concluded that speeding up window air conditioning at Bates and Fisk elementary schools is technically feasible, at an added design cost of roughly $250,000, with Superintendent David Lucier and member Suzanne Littlefield debating equity concerns since Schofield and the middle school would wait a year.

Littlefield asked, "What do you say to a Schofield parent? Why does Bates get this?" Thomas Goemaat agreed to serve as liaison on the accelerated project, and the School Committee is set to take up the issue September 22.

In the full story:

  • Solar project change orders
  • Warren DPW electric heater work
  • DPW RDF administration building
  • New business: accelerated air conditioning for Bates and Fisk
  • Minutes and invoices
  • Who Was There
  • Organizations And Documents Referenced
  • The complete report: 1,894 words

Source: the Permanent Building Committee meeting of September 10, 2026, reported from the official video recording and transcript.

Checked against the record: before publication this article was automatically compared with the meeting transcript.

Members read the rest of this story and every Norfolk County meeting we cover, in full.

Become a member

A 30-day free trial needs a payment method. After it, your membership renews at the price shown at checkout until you cancel, which you can do anytime from your account. Subscription terms

Share this story

Email Text Facebook X

Know someone in Norfolk County who follows town government? Share Townbrief Norfolk County: they can sign up free.

Share this story

Email Text Facebook X

Anyone can open a shared story. Members' stories show the free part and a sign-up line to people who are not members.